Section three · ScheduleBuilt backwards from December 1.
Development finishing is the halfway mark, not the finish line. The weeks after it are what make the difference between a system that works and a system that works on the day 300 people use it at once.
Week of September 22
Agreement and access
Service agreement signed, deposit received, access to the domain, hosting, Stripe and the current site handed over.
Late September — late October
Build
Accounts, membership, the gated sequence, ticketing, QR issuing, email, the admin dashboard and the rebuilt public site.
Late October
Board review
The board is given a working system on a private link and asked to break it. Every correction comes back into the build.
Early — mid November
Testing cycles
Full dress rehearsals: real card, real purchase, real email, real QR, real door scan. Repeated until nothing surprises us.
Before December 1
Live
Registration opens on the new system with a week of margin in hand, and someone from our side on call the day it opens.
Memorial Day weekend, May 2027
Convention
On call through the weekend. Door scanning supported live, in the room if needed.